The burn of the overall program is affected by the "slowest" team, because of dependencies. In this case, we were not the slowest team so we did not impact the overall timelines.

The alternative that I (naively?) had proposed was to just announce that we were going to be late as soon as I realized it. If we had done that, likely 2-3 other teams would have just replanned without saying anything because they were late too.

Nothing would have changed on overall timeline, just the "guilty party" would have been us.